The Spa area only will be out of action from Mon 2nd Sept – Fri 4th Oct (approximately) for roof replacement and maintenance works to the filtration equipment.
Below is a detailed plan of the maintenance:
Monday 2nd & Tuesday 3rd September:
Site establishment consisting of: Partition/Hoarding
Plastic protection over the pool
Platform construction over the pool
Demolition of existing bulkhead and existing damaged ceiling
Minor electrical works
Wednesday 4th September:
Crane to establish in the carpark to commence the removal process of the existing glass panels
Thursday 5th September:
Continuation of the removal of the existing structural steel beams
Friday 6th September:
Continuation of removal
Site measure of new Structural steel beam and stainless steel brackets to begin manufacture
From this point, there will be an approximate 1 – 2 week lead time in order to fabricate and hot-dip galvanise the beam ready for install. While this is happening works outlined below can be achieved:
- Rectify the damaged ceiling grid
- Electrical works
- Construction of the new ventilation duct
- Preliminary installation of the ventilation system
We apologise in advance for any inconveniences.